How big of a slab could I do by myself?

   / How big of a slab could I do by myself? #141  
The following week our vehicle mechanic and I found some black paint, poured a bunch of sand in it, and painted all of the vehicle pedals and steps with it so that wouldn't happen again. ;)
 
   / How big of a slab could I do by myself? #142  
Im paying $125/yard, and $100 in delivery/fuel surcharge/environmental fees. I could go to 3500 psi for about $20 more per yard; but i think thats overkill.
So, I still haven't poured my slab... Its hard to have weather, time off, advanced planning, and help, all lined up... I worked 16 straight days, problem job, pretty much 12 hrs per day. Then we had a threat of tropical weather, and then just plain rain every day for a week. Got a decent window Thursday morning; off work, no rain till evening, enough notice to get concrete ordered, But son is working Thursday/Friday...

And thats kinda the main problem with ready mix
 
   / How big of a slab could I do by myself? #143  
How big is the slab that you are going to pour?
 
   / How big of a slab could I do by myself? #144  
How big is the slab that you are going to pour?
9 ft x 20 ft x 6". right at 3.5 CY. Actually doing 3 identical slabs to create 3 full sized parking spots. Yes, I could save a few hundred by doing it all as a single pour, but I also know (or think I know) my limits. I really mostly dont want to screed and finish a 27x20.


Also, do to over site, stubborness, or whatever, I will also need to pour about a 7 ft approach slab, do to the lay of the land, and the fact that I wanted Level parking. Yes, I could build the approach with rock, but the whole yard drains that way, so I want my approach slab in concrete as well.View attachment 4200533
 
   / How big of a slab could I do by myself? #145  
.
20251008_111328.jpg
 
   / How big of a slab could I do by myself? #146  
Yes, wife did ask, how much to just hire it done vs you? Me, $2000. Hired, about $6500.

Edit: with the approach slab, im actually at $2450
 
   / How big of a slab could I do by myself? #148  
Thanks. I'm doing three pads right now. It's actually 4 pads, but I did the first one a year ago and just did the second one on Saturday. I'm going to do the next one this Saturday and the last one the following weekend.

The first one that I did last year was 10x12x6. It took almost 2 pallets of 60 pound Readi Mix from Lowes. The one I did Saturday is the same size, but I think it's thicker because I used up all of both pallets and another 6 sacks that I had in my garage. I'm digging the footing for the third pad this week and I'm going to pay more attention to not digging too deep!!!
Those three pads are for my 3 car garage. It's a low area just before you drive into the garage and a muddy mess with just gravel there. I created a low area in the middle of each pad that slope lower on each pad to carry the water away to the side of the garage, where there is a shallow ditch to take it all the way around my house.

The last pad will be 9x12x4 inches to create my new front porch.

I'm doing this by myself. It's about the max that I'm comfortable doing on my own. At 60, it wears me out, but it's doable.

I ordered six pallets and 20 sticks of 20 foot 3/8's rebar from Lowes, that they delivered and positioned for me. Having everything next to where it's going to be poured is huge. I put 3 sacks in the mixer, dump it, put 3 more in the mixer, spread what I just dumped, then dump the mixer and put 3 sacks back in again and spread what I just dumped. I do this until I have enough concrete built up at the farthest side away from the mixer that I can screed it. I'm using a 14 foot 2x6 for this. I screed about a foot at a time, trowel finish what I screed and them pile up more concrete to screed another foot. Once I get it all screed off, I use my edger and then my bull float to smooth it all out.

This takes forever, but the longer I spend doing it, the better the finish. I'll never be as good as a pro, but it's not so bad that most people will give it a second look.

557656454_10239371848297121_33324008656802527_n.jpg 558300062_10239371838736882_177521507831963721_n.jpg 559269107_10239371843737007_5623112107082790373_n.jpg
 
   / How big of a slab could I do by myself? #149  
Eddie (and Paul) -
Great!
Two questions - How do you tie in the separate pads? (or do you?) And if you just lay rebar sticking out, how much length do you run for overlap?
 
   / How big of a slab could I do by myself? #150  
Eddie (and Paul) -
Great!
Two questions - How do you tie in the separate pads? (or do you?) And if you just lay rebar sticking out, how much length do you run for overlap?
When I did my pole barn floor, I left about a foot sticking out beyond the forms to tie the slabs together. That was 9 years ago and it seems to have worked out OK.
20161020_0159.JPG
 
   / How big of a slab could I do by myself? #151  
When I did my pole barn floor, I left about a foot sticking out beyond the forms to tie the slabs together. That was 9 years ago and it seems to have worked out OK.
View attachment 4201036
That's the same way I did our garage addition... by running the rebar through the form. It helped to keep the rebar in the center of the slab, and I used chairs wired to the underside of the rebar as well throughout the slab.

When I did the adjacent slab, I'd just wire it with that 12-18" overhang in two places so it couldn't shift, and I ran a piece perpendicular across the joints and wired them. It wasn't going anywhere. ;)
 
   / How big of a slab could I do by myself? #152  
See post #62 in this thread. šŸ™ƒ


First slab ready to pour...
(click to enlarge)
IMG_7365.jpeg

Second slab ready to pour...
(click to enlarge)
You can see the rebar for the 1st slab tied to the 2nd slab.
I used 2x6 so the concrete is about 5-5.5" thick.

IMG_7366.jpeg
 
   / How big of a slab could I do by myself? #153  
Eddie (and Paul) -
Great!
Two questions - How do you tie in the separate pads? (or do you?) And if you just lay rebar sticking out, how much length do you run for overlap?
There are two opposite opinions; 1) tie them together with rebar dowels, maybe bonding agent, or a "key way" joint.(structural slabs are like this)
Option 2), dont bond them at all, actually put expansion joint between them, and allow them all to float separately (sidewalk and driveways are normally like this)

For me, I have kinda gone back and forth on to tie or not; but I have settled on my slabs, im going to do an expansion joint between them, and then run a poly bulalyne(sp?) caulk sealer over the expansion joint.
 
   / How big of a slab could I do by myself? #154  
So, as a rough guideline, with exceptions, if it has a footer, you really should avoid cold joints, and have a way to bond the slabs together, rebar, epoxy dowels, key ways, ect

Generic, no footer, not taking point loads, expansion joint and no structural connection (sidewalks, driveways, pool barn floors, ect)

To construct a Keyway joint, you nail a 1x2 or 2x2 on the form boards of pour one, creating a socket, bell, or grove when the form is stripped. Then the 2nd pour creates the spigot, tennon, tongue; locking them together. Additionally, the cold/cured concrete can be coated with a bonding agent. The rebar dowels left flying (as shown) work, as does a flat face, and drill and epoxy dowels in prior to the 2nd pour.
 
   / How big of a slab could I do by myself? #155  
Im not great with words, so here's a picture if a keyway
Screenshot_20251008_160219_Google.jpg
 
   / How big of a slab could I do by myself? #156  
Generally sidewalk, driveways, and non load bearing slabs are kinda treated as non structural, and they typically use an expansion joint between pours.
Screenshot_20251008_160527_Google.jpg
 
   / How big of a slab could I do by myself? #157  
See post #62 in this thread. šŸ™ƒ


First slab ready to pour...
(click to enlarge)
View attachment 4204377

Second slab ready to pour...
(click to enlarge)
You can see the rebar for the 1st slab tied to the 2nd slab.
I used 2x6 so the concrete is about 5-5.5" thick.

View attachment 4204379
If you look at picture one above, I had to drill and epoxy pins into the existing garage foundation so the new slab(s) would be tied to the old slab and wouldn't move around. I tied the pins to the rebar in the new slab(s).
 
   / How big of a slab could I do by myself? #158  
The argument against dowels, lets say my approach slab, if the slab settles, its either going to simply settle maybe 3/4" and thats it, with no dowels, or crack, and break, but still settle the same with dowels.
If I was doing a full rebar mat, with bends at the right points, and tied to dowels, yes, you could effectively bridge the settled material, but its not really the same as throwing rebar in. The rebar is strategically placed to counter act specific load points, some place towards the top of the concrete, and in other places towards the bottom, to take the tension in the "beam".

Not to nerd out too much about loads and beams
 
Last edited:
   / How big of a slab could I do by myself? #159  
The argument against dowels, lets say my approach slab, if the slab settles, its either going to simply settle maybe 3/4" and thats it, with no dowels, or crack, and break, but still settle the same with dowels.
That's why I put 4' deep 12" sonotube down every 8' along the outside edges and between slabs, in addition to the pins in the existing slab, and in addition to the 12" deep by 12" wide footing all the way around. It's not going anywhere, ever. šŸ™ƒ
 
   / How big of a slab could I do by myself? #160  
If I don’t tie the expansive soil causes shifting…

For small sidewalks I use roto-hammer with 20 penny nails.

For slabs it’s extending the 1/2 inch rebar into the new pour 18ā€ or longer if the rebar runs wild.
 

Marketplace Items

GRID SHAPED BUCKET FOR MINI EXCAVATOR (A58214)
GRID SHAPED BUCKET...
2015 Peterbilt 348 Dump Truck (A55973)
2015 Peterbilt 348...
500 BBL FRAC TANK (A58214)
500 BBL FRAC TANK...
CATERPILLAR D6K2 LGP CRAWLER DOZER (A60429)
CATERPILLAR D6K2...
HUSQVARNA RIDING MOWER 42IN DECK (A56859)
HUSQVARNA RIDING...
JCT 48" HYD TRENCHER (A52706)
JCT 48" HYD...
 
Top