POLE BARN ATTIC WORK

   / POLE BARN ATTIC WORK #21  
Why not get some joist hangers and some 2x6x8'. Nail them 11" apart on their splines and and then some 3/4" T&G OSB decking cut to 2' by 8" sections nailed on top. It would be like a cat-walk.... Those hangers should be enough to hold everything.
 
   / POLE BARN ATTIC WORK #22  
Why not get some joist hangers and some 2x6x8'. Nail them 11" apart on their splines and and then some 3/4" T&G OSB decking cut to 2' by 8" sections nailed on top. It would be like a cat-walk.... Those hangers should be enough to hold everything.

I would not use 8'ers. his span is 8 ft apart.

Wouldnt it be better to get wood I-joists that are already 40 ft long. Make a box with 3/4 osb 2-3 ft wide on top of flange of bottom i joist screwed in . Make sure the I joists are staggered throughout the 60ft span. This will give you sides for protection as you walk along and give you a place to put wiring on the top of i joist. If there is room in the trusses, put it on top of span trusses instead of using hangers.
 

Tractor & Equipment Auctions

2007 Amkus Rescue System (A50322)
2007 Amkus Rescue...
Vacuworx Vacuum Lifter Pad (A50860)
Vacuworx Vacuum...
2021 CATERPILLAR 953 CRAWLER LOADER (A51242)
2021 CATERPILLAR...
(2) ROLLS OF HD CHAIN LINK MESH WIRE (A50460)
(2) ROLLS OF HD...
2015 John Deere 35G Mini Excavator (A49461)
2015 John Deere...
2004 John Deere 9320 Articulating Tractor (A50860)
2004 John Deere...
 
Top