When to pour concrete

/ When to pour concrete #1  

sawtooth

Veteran Member
Joined
Sep 19, 2007
Messages
1,194
Location
Eden NC
Tractor
Ford NAA, Ford 2810, Ford 3910-1, Ford 3910-2, Ford 4600SU, Massey 2660 HD, Massey 461, Grasshopper 725D, Grasshopper 900D
Well I'm a little concerned and need some advice. I have a farm in Ohio and am in process of building a barn on slab foundation. Problem is that it was supposed to be poured in October but never happened. Now its getting very cold and Ive been told cold weather is bad for pouring concrete. So should I proceed or wait till spring? My contractor doesn't seemed worried but I am.

Thank you
 
/ When to pour concrete #2  
We need some more info. Is the building heated at all? Is the slab insulated in anyway?
 
/ When to pour concrete #3  
Plus, they can add an additional curing agent so it cures faster as well. I think lime is one of them. B.
 
/ When to pour concrete #4  
You do not want to pour on frozen ground period ! If it hasn't frozen yet your good. You will want to keep the pour covered until it has cured to prevent from freezing. This time of year you really need to watch the weather. If you see a few good days of fair weather ahead that would be the time to do it. I would not pour if the forecast is in the teen's and 20's.
 
/ When to pour concrete #5  
Calcium is what they add I believe.
There's no problem pouring in the winter or almost any condition for that matter, they adjust the calcium contents to the order.

If you trust your contractor to pour the poundage psi you require/want along with the finished product temps won't be a problem.
 
/ When to pour concrete #6  
FDOT (Florida department of transportation) requires 40 degrees and rising at the time of pour. I would try to follow that.

Calcium: I know it was strictly forbidden in post -tension slabs because it could eat the cables up over time (or at least thats what I was told). I realize your probably not doing post tension, but does calcium eat rebar and WWF? I dont know, but might be worth asking.


Edit. I belive its calcium chloride they add
 
/ When to pour concrete #7  
I've been 'getting to' level, frame and pour a 40X12 patio slab out back for wifey all summer and fall and just haven't gotten to it yet. My neighbor, who has his own concrete business, says if I add 'antifreeze' to the mix, which is listed as 'other' cost from my supplier, I'd be good down to about 30*. Having worked in the construction industry for over 40yrs of my life, I think he's full of @*%#. Have seen the effects of too cold cure, too fast cure and ethelyne glycol being added under wrong (too cold) conditions that have caused extensive spalling, severe cracking, dips and not having the psi rating you pay for. IMHO I wouldn't pour or let concrete set to cure in temps any lower than about 38*-40*. This is for an outside pour with no insulation/gravel. Too many companies do cold weather pours solely for profits, as the rates they pay their help they can afford to keep sending someone back to do repairs. Don't do it Sawtooth - wait for spring!
 
/ When to pour concrete #8  
There are perfect scenarios but in the early 70's I remember working for companies ordering and pouring cement at anytime of year. Was it preferable to do it during warmer times? Yes. But it was done at all times of the year even if we had to shelter with plastic and run space heaters to keep the top water layer from freezing and it was done in commercial buildings with strict guide lines with sample tests.
One of the last ones I remember well was a 5000# floor in open air with only a roof and one wall, the temp was close to zero the morning of the pour.
I ruined a good pair of boots and gloves on that one but to this day it hasn't cracked or buckled and still maintains the pitch we finished it to.
 
/ When to pour concrete #9  
There are perfect scenarios but in the early 70's I remember working for companies ordering and pouring cement at anytime of year. Was it preferable to do it during warmer times? Yes. But it was done at all times of the year even if we had to shelter with plastic and run space heaters to keep the top water layer from freezing and it was done in commercial buildings with strict guide lines with sample tests.
One of the last ones I remember well was a 5000# floor in open air with only a roof and one wall, the temp was close to zero the morning of the pour.
I ruined a good pair of boots and gloves on that one but to this day it hasn't cracked or buckled and still maintains the pitch we finished it to.

Although ive never worked north of Statesboro GA, I know and understand that on a major project, you cant simply wait six months to pour a slab, but they take extraordinary measures to do it. I dont know Ohio, but surely it gets into the 40s and 50s sometimes during the winter. Takes some planning, and a little luck, but I would try to pour at 40+, and if you use high early strength, even better.
 
/ When to pour concrete #10  
my wife is a CE doing RE (resident engineer) work onsite at a new road building project. they follow IDOT regs which state they can not pour concrete unless the temp is 35 deg and riseing.

IDOT does not allow the use of additional curing agents for freezing weather. (at least when pouring 10" thick concrete that is going to be used for road)
 
/ When to pour concrete
  • Thread Starter
#11  
Im going to tell him to put off the job. Im pissed that i gave him a deposit in early october and now have to wait but I want it done right. This will be done out in the country so theres no hot water and no heaters. Slab has to be done first so no building over it or insulation. Not a happy camper right now but very much appreciate the info from everyone.
 
/ When to pour concrete #12  
Good idea to wait. Suppose to be in the teens for a few nights. Should have air temps above 35 degrees and if you are on site, be sure the slump is around 4 inches. Too many are poured with slumps of 5 or 6 or more and then the owner wonders why the slab cracks or flakes. Too much water and you lose the strength of the concrete. They just poured a basement wall down the road a few days ago and the forms are already off. I would not want that house. Forms should be on for at least 7 days and weather in the teens and 20's without being enclosed and heated is not good for concrete strength.
 
/ When to pour concrete #13  
Good idea to wait. Suppose to be in the teens for a few nights. Should have air temps above 35 degrees and if you are on site, be sure the slump is around 4 inches. Too many are poured with slumps of 5 or 6 or more and then the owner wonders why the slab cracks or flakes. Too much water and you lose the strength of the concrete. They just poured a basement wall down the road a few days ago and the forms are already off. I would not want that house. Forms should be on for at least 7 days and weather in the teens and 20's without being enclosed and heated is not good for concrete strength.
I have been doing this for a while now. I can say when walls are poured today the forms are removed tomorrow. As for leaving them on due to the cold that is what heat blankets are for not what the forms are for.
 
/ When to pour concrete #14  
If You Have frost in the ground , You Must get it out first. If not cover the area with concrete blankets (You Paid a deposit ? see if he will supply his), Or a heavy layer of straw and wait for a decent stretch of weather.In Cooler weather if the slab you are pouring ,you want 4000 psi , get 4500 psi . Get a NO flyash mix . Use an exterior mix (with air ) Unless you are covered and can pour and have heat inside. don't use turbo heaters or something like those as they will cause the surface to dust. The ready mix can provide you with Heated ag and water and will bring the concrete temp up to at least 75 Degrees. You can ad calcium chloride up to 2% , Yes over time it can eat your Rod/wire. You can get a noncorrosive accelerator which is about double the cost of Calc.Chloride. Wait for a day and nite combo of temps above freezing and pour your Concrete! Finish and cover with Concrete blankets. Leave them on a few days but make sure they come back the next day to saw the joints and recover. They should not uncover the slab all at once and send it into shock. A good rule of thumb to remember is , once the concrete reaches 500psi (about the time you can walk on it to finish) it can go thru a freeze thaw cycle and continue to gain strength. Or just wait for spring . But I would not be afraid to pour in cold weather. I Batch Concrete to Contractors and on state jobs every day.
 
/ When to pour concrete #15  
Im going to tell him to put off the job. Im pissed that i gave him a deposit in early october and now have to wait but I want it done right. This will be done out in the country so theres no hot water and no heaters. Slab has to be done first so no building over it or insulation. Not a happy camper right now but very much appreciate the info from everyone.
GOOD MOVE!
Better to wait till spring than have major problems for life. If he couldn't GUARANTEE in writing it would be problem free it probably wouldn't be problem free.

Concrete is not very forgiving.
 
/ When to pour concrete #16  
/ When to pour concrete #17  
I wanted my driveway done around Christmas. They did not get around to doing it until January 2. The temp dropped from cool to windy and bone cold. Lower 20's or so with the ground starting to freeze. In Georgia 20's is cold, or maybe I should say in Atlanta. The base was gravel I had been driving on the past 15 years. They added a bag of calcium to each truck. They tooled in the control joints when the concrete was wet. No protection from wind or cold. 2 years later and I see hairline cracks where they did the joints. Control joints did what they were supposed to do. No visible change in grade or plane. I really did not believe it was good time to do concrete but so far so good. Maybe when I am 75 in 20 years I will be annoyed. On the other hand the other driveway slab poured in the summer/early fall 18 years ago is cracked where cut control joint are not. That slab was on fill that was probably not properly compacted.

I do need to caulk those hairline cracks in the new driveway and the bigger cracks in the older driveway.

My car weighs 3,500 pounds. The truck 6,000 pounds. The truck and trailer hauling hay only weighs 12-13,000 pounds over 4 axles so my driveway never gets any real weight on it.
 
/ When to pour concrete #18  
Here is the specification for cold weather concrete placement used on military construction:
"3.8.6 Cold Weather
ACI/MCP-2. Do not allow concrete temperature to decrease below 10 degrees C
50 degrees F. Obtain approval prior to placing concrete when the ambient
temperature is below 4 degrees C 40 degrees F or when concrete is likely to
be subjected to freezing temperatures within 24 hours. Cover concrete and
provide sufficient heat to maintain 10 degrees C 50 degrees F minimum
adjacent to both the formwork and the structure while curing. Limit the
rate of cooling to 3 degrees C 37 degrees F in any 1 hour and 10 degrees C
50 degrees F per 24 hours after heat application.

On military projects anti-freeze products such as calcium are not allowed. Exterior concrete is always minimum 4-6% air entrainment. It costs more but specifying "high nearly cement" and water reducing additives and 2" slump will reduce the curing time greatly and shorten the heating time. The sub-grade cannot be frozen and should be at the same 40-50 degree temp. The average finisher will hate you for following this spec, but ACI certified finishers knows this stuff and is used to following it. Well specified commercial work follows the same spec as it is proven success formula tested and approved by the American Concrete Institute.

If you cannot or do not want to pay for this procedure wait till spring. An ACI supporting contractor will guarantee his work butg there is a cost associated with proper workmanship.

Ron
 
Last edited:
/ When to pour concrete
  • Thread Starter
#19  
Thanks Ron. I contacted the builder this am and said to hold the project till spring. Not happy with this but too much money to jeopardize project so will just have to wait. Thanks for the info though.
 
/ When to pour concrete #20  
I have been doing this for a while now. I can say when walls are poured today the forms are removed tomorrow.

During the summer we were working at a house in new construction. They were pouring the house on the lot next to us. They started the pour around 7 AM and had it done by around 10 - poured that is ... still needed some secrete work. The forms were off before they went to lunch.
 
 
Top