Pole building question

/ Pole building question #1  

Newtocvt

Bronze Member
Joined
Apr 11, 2017
Messages
99
Location
Menomonie,Wisconsin
Tractor
New holland 54d
I am thinking of building a pole building for general storage. Mostly for implements I don't want to leave out all winter. I don't need an insulated or heated building and was thinking about just gravel floor. Size wise I was thinking about 24x32 with one 9 foot garage door and a service door. No windows. The area I am thinking about slopes 2-3 feet over the 32' span. My question is can I set the post before the site is leveled and graded. My theory is I can set the post 4 feet deep with my post hole digger than the back full and gravel would essentially make the 6-7 feet deep. Any thoughts?
 
/ Pole building question #2  
I am thinking of building a pole building for general storage. Mostly for implements I don't want to leave out all winter. I don't need an insulated or heated building and was thinking about just gravel floor. Size wise I was thinking about 24x32 with one 9 foot garage door and a service door. No windows. The area I am thinking about slopes 2-3 feet over the 32' span. My question is can I set the post before the site is leveled and graded. My theory is I can set the post 4 feet deep with my post hole digger than the back full and gravel would essentially make the 6-7 feet deep. Any thoughts?


I think you will find it to be more than a major nuisance to be grading around posts already set.
 
/ Pole building question #3  
That. Even if it means you build a retaining wall.
Jim
 
/ Pole building question #4  
And do have a bldg code? Around here you'd need to have a footing under each post, inspected before backfill. Not a bad idea, even for storage.
Jim
 
/ Pole building question
  • Thread Starter
#6  
No building code here. I already checked with the township only thing they care about is the road setbacks. It sounds like I should just get the area prepared first.
 
/ Pole building question #7  
Prior proper preparation prevents poor performance.
 
/ Pole building question #8  
Couple of things we had a high lift level our pad and really compact it so it shouldn't settle. Second if you do metal I highly recommend insulating the roof or it is going to sweat and drop water on your implements, the bumble wrap to do my 30x40 was an extra 300$ well worth it. I would level, compact then set your posts
 
/ Pole building question #9  
I had a couple feet of fill added for my pole shed and had a driveable vibratory roller go aver it a couple times. When I had to dig for some plumbing pipes I had a difficult time shoveling and picking through it. That is a good thing and money well spent.
 

Marketplace Items

2025 Greatbear Rachet Tie Down & Flatpack Tool Box (A61567)
2025 Greatbear...
(6) 150 TON MOVERS (A64280)
(6) 150 TON MOVERS...
2006 PITTS 4 BOLSTER LOG TRAILER (A64276)
2006 PITTS 4...
UNUSED SDLANCH SDLGC80 ELECTRIC GOLF CART (A64280)
UNUSED SDLANCH...
2019 HYDREMA MX14 TIER 4 MOBILE EXCAVATOR (A63276)
2019 HYDREMA MX14...
1993 WhiteGMC WG Tri-Axle Dump Truck (A61573)
1993 WhiteGMC WG...
 
Top