I'm building a pole buidling in about two months and plan on running electricity to it before next winter. Would #10 wire be as good as I need and should I run two wires? Here is some more information:

- I plan on dropping in additional breaker in the house fuse box and connecting the pole buidling to the house and putting in a small fuse box at the barn
- The buidling will be about 400 feet from my house
- I will run lights most of the time and a fan in the summer and maybe a tv/radio
- I will also run a compressor and possibly a small table saw and small hand tools and probably a charger for my tractor on occasions.
- No plan to hook up heater as I have a wood buring stove