ADin
Silver Member
As I'm currently on the fence between buying a 4110 and waiting to at least hear info on the impending new models (2X2X ??), I'm looking for guidance from some of the veterans here who have seen this process unfold before.
I would normally expect rumors on new models to be followed by credible leaks of real information, followed by official announcements, followed by true availability.
My question: As JD seems to be able to control information pretty tightly, is there a historical rule of thumb in the duration from the time of credible leaks of real information and/or official announcements to actual shipping availability of product. I realize the rumor phase is an indeterminate time period, but leaks typically start as the rollout process (at least internally) requires furthur distribution of committed information to broaded audience (e.g. dealers). Does JD announce product weeks/months before availability or days/weeks?
My main reason is given that it's now early May, I'm trying to decide best case/worst case senarios.
One senario for example (probably best case) is that true leaks of information start appearing over the next week or two, official announcement sometime early June and maybe a tractor on my lawn sometime in July.
A second senario is continued speculation most of May, leaks May/June, announcement perhaps July, availability late August/Sept in very limited quantity and only to tier one dealers, and finally tractor in lawn for last cut of the season.
Obviously there are infinite variations here but which of the above has a 70% chance of being accurate as the latter effectively looses the 2005 year for playing in the dirt and I might be inclined to go the plunge for a 4110 now versus waiting one month to decide my options.
Murphy's law says my decision will be wrong in either case but I would kick myself if I plunged too quickly and missed the opportunity to get a cup holder on the 4110 replacements
I would normally expect rumors on new models to be followed by credible leaks of real information, followed by official announcements, followed by true availability.
My question: As JD seems to be able to control information pretty tightly, is there a historical rule of thumb in the duration from the time of credible leaks of real information and/or official announcements to actual shipping availability of product. I realize the rumor phase is an indeterminate time period, but leaks typically start as the rollout process (at least internally) requires furthur distribution of committed information to broaded audience (e.g. dealers). Does JD announce product weeks/months before availability or days/weeks?
My main reason is given that it's now early May, I'm trying to decide best case/worst case senarios.
One senario for example (probably best case) is that true leaks of information start appearing over the next week or two, official announcement sometime early June and maybe a tractor on my lawn sometime in July.
A second senario is continued speculation most of May, leaks May/June, announcement perhaps July, availability late August/Sept in very limited quantity and only to tier one dealers, and finally tractor in lawn for last cut of the season.
Obviously there are infinite variations here but which of the above has a 70% chance of being accurate as the latter effectively looses the 2005 year for playing in the dirt and I might be inclined to go the plunge for a 4110 now versus waiting one month to decide my options.
Murphy's law says my decision will be wrong in either case but I would kick myself if I plunged too quickly and missed the opportunity to get a cup holder on the 4110 replacements