Approximately how long to brushhog 35 acres with 65hp tractor and 7’ cutter? Guesstimate.
 
   / Brushogging #3  
Somewhere around 10 hours, at 4mph. That's assuming full 7 foot cut every pass, no doubling back, no over lap, no BSing around. Now, if you can pull off 4.5 mpg average, it will be a bit faster.

I think 4mph is a pretty good number for a field, but if there are obstacles, heavier brush, ect, it could very well be 3 mph, or 14 hours.
 
   / Brushogging #4  
Somewhere around 10 hours, at 4mph. That's assuming full 7 foot cut every pass, no doubling back, no over lap, no BSing around. Now, if you can pull off 4.5 mpg average, it will be a bit faster.

I think 4mph is a pretty good number for a field, but if there are obstacles, heavier brush, ect, it could very well be 3 mph, or 14 hours.
4mph would be too fast for me. I do about 35 in 3 6 hour days. I have 75Hp with 8’ cutter. Impossible to not have overlap and turns etc. This is brush cutting not finish mowing.
 
   / Brushogging
  • Thread Starter
#5  
Somewhere around 10 hours, at 4mph. That's assuming full 7 foot cut every pass, no doubling back, no over lap, no BSing around. Now, if you can pull off 4.5 mpg average, it will be a bit faster.

I think 4mph is a pretty good number for a field, but if there are obstacles, heavier brush, ect, it could very well be 3 mph, or 14 hours.
Kinda what I was thinkin. 12 -15 hrs. Just gitting other opinions. Thanks.
 
   / Brushogging #6  
Somewhere around 10 hours, at 4mph. That's assuming full 7 foot cut every pass, no doubling back, no over lap, no BSing around. Now, if you can pull off 4.5 mpg average, it will be a bit faster.

I think 4mph is a pretty good number for a field, but if there are obstacles, heavier brush, ect, it could very well be 3 mph, or 14 hours.

At 4 mph, and a full 7 ft cut with a field 7 ft wide by 41.26 miles long, it would take 10.34 hours.
 
   / Brushogging #7  
One thing that we can't speak to, is your unproductive time. That's turning, lining up your passes, stopping to 'water the grass', ect; and it adds up more than people think, especially on anything odd shaped.

I would throw a guess out there, that maybe your 85% efficient; so if you are bidding this for someone else; I would use the 14.38 hours at 85% efficient; I get 16.91 hours total job.
 
Last edited:
   / Brushogging #9  
If you are mowing a unknow field, you may want to double the hours mentioned above in order to have time to react to possible hidden objects. Ken Sweet
 
   / Brushogging #10  
is this for hire or your own? i'm always skeptical of unknown fields, esp hardware w/loaded rear tires.
 

Tractor & Equipment Auctions

TANK MANIFOLD (A55745)
TANK MANIFOLD (A55745)
Stainless Steel 1" Spool (A52377)
Stainless Steel 1"...
RIGID TOOLBOX (A52472)
RIGID TOOLBOX (A52472)
2010 Ford Transit Connect Cargo Van (A53422)
2010 Ford Transit...
Hose Reel (A53425)
Hose Reel (A53425)
2008 24ft. Haulmark Edge T/A Enclosed Trailer (A52377)
2008 24ft...
 
Top