Concrete floor help!

/ Concrete floor help! #1  

Willman

Gold Member
Joined
Nov 18, 2004
Messages
397
Location
Southeast PA.
Tractor
Mahindra 4110
I am looking to pour a concrete floor in my existing 24" x 40" pole barn.
I was thinking of a 5 - 6 inch slab.
I will need to dig out so as to keep the existing door opening height.
These are my questions:
1. How thick should the stone subbase be?
2. Should I just pour up to the outside wall poles leaving a space between the slab and outside steel walls?
3. Should I put a drain in the floor somewhere in the middle?
Thanks for any input you may have.
 
/ Concrete floor help! #2  
Willman,

I just had a little barn built. The slab was poured between 6 and 8 inches thick. I have no drains so it is sloped to the door.

I'd say you would need 4 to 6 inches of gravel below the slab since your not in a foundation. How high is the watertable in that area? Do you need curtain drains under the floor?

If you poured up to the siding would you put a form on the outside?

Regards,
Chris
 
/ Concrete floor help! #3  
</font><font color="blue" class="small">( 3. Should I put a drain in the floor somewhere in the middle?)</font>

As long as the inspector isn't involved, you may get away with it. There are environmental issues with garage floor drains. Gerard
 
/ Concrete floor help! #4  
1. How thick should the stone subbase be?
I put down about 12 inches of mixed stone, tamped at about 6 inches and again on top.

2. Should I just pour up to the outside wall poles leaving a space between the slab and outside steel walls?
I poured right against my bottom girder, but mine is wood. I don't know about a steel building.

3. Should I put a drain in the floor somewhere in the middle?
It is nice to have floor drains, but if your local building inspector is involved, he would like to have a chat with you about where they drain to. I know towns in my area are begining to get very strict with any kind of drainage.

Good luck with the pour. If your going to run a power float, be prepared to take it easy the next couple of days. Your body will be sore.

Dave
 
/ Concrete floor help! #5  
4" sub-base should be fine for your climate. the floor drain issue is that is would not be connected to any city sewer system. in case there is a hazardous spill in the building. check with your local codes to be sure. put some plastic 6 mil down on the sub base and your steel mesh unless your using fiber reinforced mix..
 

Marketplace Items

2006 HONDA RANCHER ATV (A62130)
2006 HONDA RANCHER...
2015 Chevrolet Express 2500 Passenger Van (A61568)
2015 Chevrolet...
2023 New Holland CR10.90 Combine - 330 Engine Hours - 251 Separator Hours (A56436)
2023 New Holland...
2015 LOAD TRAIL 24+6 GOOSENECK TRAILER (A58214)
2015 LOAD TRAIL...
2012 Volkwagon Passat Sedan (A61569)
2012 Volkwagon...
1998 Link Belt HTC-8660 60 Ton Hydraulic Truck Crane (A60352)
1998 Link Belt...
 
Top