Can't build mine for another couple of years but we have good steel kits available and there is lots of competition from different manufacturers. Concrete is probably the dearest bit.
$25.53/ft. by today's price. 38 years.Here is a way to put the cost in perspective.
38 years ago I had a 14' x 36' x 48' Morton put up.
Cost was $12,500 including floor.
That worked out to be $7.23 per sq. ft.
I thought that was expensive ......THEN!
BTW: My Morton building still looks great, and lives only 1/2 mile from the salt water.
I just had a 24'X40'X10' steel pole building put up. Cost for material and labor was right at $19,000 (Man door, two windows and one 18' garage door). I have to have the concrete floor poured, and am figuring about $5K for that. I figure with electric and radiant heating system installed in floor, I'll be right around $30,000.
This outfit is just down the road from me.
Service Area | Pole Barns Direct