Progress continues....
I finally finished getting all the rock out, and of course the last part was by far the hardest, quite literally. I then located all the corners and drilled holes to mark them, and stuck rebar in the holes. These points aren't super accurate, but close enough for me to now backfill and compact around all the remaining ledge.
I had pushed rubble and tailing into the dips and valleys to make it possible to move my excavator around in the foundation site. Now I got to dig it all back out, and fill with compacted granular fill. It's been an interesting exercise in filling in sections to gain access to fill in other sections. But sure enough, one lift at a time, it's slowly coming up to grade.
Here we are just getting started filling the first valley.
Then expanding around the ledge....
And further to access an adjacent valley. It's like a glacier working it's way down a valley, and progresses at about the same speed :-(
Then on to start filling other valleys...
At the end of day 3, 2/5ths of the site is within a few inches of grade. The remaining 3/5ths still needs to come up an average of 12-18". I'm almost through the last of 4 loads of fill at 14 yds each, and have 4 more coming tomorrow. I think I only need 3, but would rather have too much and can always use leftovers around the driveway.