I paid my builder for the labor cost of constructing my shop last week. In that bill was $1000 for use of his SkyTrak. That was a bargain. Saved me twice or three times that much labor.
 
   / Starting our new life #362  
Yes, and the picture does not due it justice to how long the runs are. 70' long each. You would think it's for a hotel, but that's what was required.:confused3: I'm just glad it's behind me.:laughing:

The trusses are supposed to be delivered today.:drink: The house should move along pretty quick now.

I just finished my drain field-try 5 100’ laterals!! My drainfield is larger than some people’s building lots!
 
   / Starting our new life
  • Thread Starter
#363  
I just finished my drain field-try 5 100’ laterals!! My drainfield is larger than some people’s building lots!

It's as if the Health department is saying "don't build", we are going to make it as costly as possible. At least you too have it behind you. :thumbsup:
 
   / Starting our new life #364  
All specifications that I have seen for road construction state inspector can review items multiple times, not one bite at the apple. Also be nice to inspectors they can make life terrible if you have to follow every rule exactly
 
   / Starting our new life
  • Thread Starter
#365  
Found out today the framers will not show up until Monday next week. :mad::banghead: They did say they would stay until the job was finished. :thumbsup:

There was some good today. Rocky Mountain Power showed up to get my power installed. :D They have the pole in and the main power pulled into the conduit from the pole. Tomorrow they will hook up both ends, install the transformer and pull the power to my house panel.

I have been waiting for the power so I could get my well pump installed and wired up. I'll get that done next week.:thumbsup:


DSCN3228.JPG
 
   / Starting our new life #366  
Love watching your progress and scenery!
 
   / Starting our new life
  • Thread Starter
#367  
Love watching your progress and scenery!


Thanks,

I'm dying to take some pictures of the view out the back of the house (wall of glass) once the framing is done. Hopefully I can do it while the leaves are still bright red.
 
   / Starting our new life #370  
Found out today the framers will not show up until Monday next week. :mad::banghead: They did say they would stay until the job was finished. :thumbsup:

There was some good today. Rocky Mountain Power showed up to get my power installed. :D They have the pole in and the main power pulled into the conduit from the pole. Tomorrow they will hook up both ends, install the transformer and pull the power to my house panel.

I have been waiting for the power so I could get my well pump installed and wired up. I'll get that done next week.:thumbsup:


View attachment 571762

That truly is "big sky country". :)
 

Tractor & Equipment Auctions

GENERATOR 24GF-LDE 25KW (A50854)
GENERATOR 24GF-LDE...
2011 Nissan Titan SV 4x4 Crew Cab Pickup Truck (A50323)
2011 Nissan Titan...
71066 (A49346)
71066 (A49346)
Bus (A50323)
Bus (A50323)
CRESCENT SUPPLY 20 CONTAINMENT TRAILER (A50854)
CRESCENT SUPPLY 20...
2007 Jeep Liberty (A50515)
2007 Jeep Liberty...
 
Top