My shop is under construction

   / My shop is under construction
  • Thread Starter
#21  
Here is a close up of the top of the truss. I will be out of town for the next 3 days. Hopefully when I get back I can post completed pictures.
 

Attachments

  • 768819-Building truss top.jpg
    768819-Building truss top.jpg
    34.6 KB · Views: 541
   / My shop is under construction
  • Thread Starter
#22  
I was hoping that by the time I got back Saturday they would be finished, but they didn't make it. They still have the west side siding and insulation left to do, install the 2 walk through doors, and finish putting the roof over the open end, and add the corner trim.
 

Attachments

  • 770707-Back side view.jpg
    770707-Back side view.jpg
    51.2 KB · Views: 476
   / My shop is under construction
  • Thread Starter
#23  
All siding is up except this end.
 

Attachments

  • 770709-Roll up door end.jpg
    770709-Roll up door end.jpg
    36.8 KB · Views: 496
   / My shop is under construction
  • Thread Starter
#24  
It is insulated. This is looking back to where the bath room will be.
 

Attachments

  • 770710-Inside view.jpg
    770710-Inside view.jpg
    40.5 KB · Views: 545
   / My shop is under construction #26  
Looking good!! you are on a roll /forums/images/graemlins/smile.gif won't be much longer and you'll be ready for winter... /forums/images/graemlins/cool.gif

Man talk about fast!!
 
   / My shop is under construction
  • Thread Starter
#27  
We got rained out Monday and Tuesday. This afternoon I will take some more pictures of the progress.
 
   / My shop is under construction
  • Thread Starter
#28  
Today was the 9th day that they worked on my shop. They got all of the roof on, and the west end wall around the roll up door installed. The builder called this afternoon and said that he would have the trim and the 2 personnel doors on tomorrow and he should be finished by 1:00. We will see.
 

Attachments

  • 772897-Building 9th day.jpg
    772897-Building 9th day.jpg
    38.5 KB · Views: 444
   / My shop is under construction
  • Thread Starter
#29  
From the other corner.
 

Attachments

  • 772899-Building 9th day 2.jpg
    772899-Building 9th day 2.jpg
    40.9 KB · Views: 372
   / My shop is under construction
  • Thread Starter
#30  
The shop is finished. It took them 10 days start to finish. Here is the west end with a 10ft roll up door.
 

Attachments

  • 774067-FInished end.jpg
    774067-FInished end.jpg
    38.3 KB · Views: 397
   / My shop is under construction
  • Thread Starter
#31  
A shot of the north side. I need to paint my doors to match. Right now they are gray.
 

Attachments

  • 774068-FInished side.jpg
    774068-FInished side.jpg
    43.8 KB · Views: 468
   / My shop is under construction
  • Thread Starter
#32  
This is the east end with a 20ft covered area. I will keep my tractor, Gator, and anything else that has muddy tires there.
 

Attachments

  • 774069-Finished Backside.jpg
    774069-Finished Backside.jpg
    53.8 KB · Views: 519
   / My shop is under construction #34  
Very nice!!!!

I love the covered storage area.

Eddie
 
   / My shop is under construction #35  
My dad is looking at polebarn kit that is very similar to yours. I remembered your project when he showed me pictures of the kit. Now that you have had it for a few months, Are you stil pleased with it? Is there anything you would do different? And , Is there anything that you can think of that we should be aware of? Thanks, Mudcat
 

Marketplace Items

1998 PETERBILT 377 MIDROOF SLEEPER (A58214)
1998 PETERBILT 377...
2012 Ford F-350 4x4 Ext. Cab Pickup Truck (A59230)
2012 Ford F-350...
2016 John Deer 5075E (A60462)
2016 John Deer...