PaulT
Gold Member
I have a gravel road leading to my house as well. It is about 850 feet long, and your picture appears to be similar in construction, from what I can see. 2 years ago, we had a major addition built, beginning in April (very wet season for upstate NY). The builder got a cement truck stuck up to its axles!!! They had to get a crawler/loader in to get it out. It turns out that the roadbed was never built, and the previous owner just kept putting #2 gravel on the mud, only to have it repeatedly disappear. The original house must have either been built during the summer or winter, when the clay hardpan/mud was solid as a rock, or during an exceptionally dry spring or fall, or they would have lost a truck or two as well. Enough of the story, how did we fix the problem, you ask?
The entire driveway was covered with rip-rap (also called cobbles, basically 4-5 inch stone chunks). This was left in place for the duration of the building process (about 4 months), to let the heavy equipment drive it into the ground. Then, on top of this, we spread 2-4 inches of #2 gravel. The gravel still disappears, but not at such an alarming rate. Now that I have a box blade, I can dig it up and re-spread it, too.
My recommendation is to dump the rip-rap in early spring, when its really wet, so it will sink in. This will also have the effect of leveling the low spots, more or less. I was able to drive my Saab 9000 over the big rocks, with only a little clunking, if I drove slowly and carefully. After the wet season is nearly over, have the trucks come back with #2 crushed (not washed or round, you want the little dusty stuff, too). Spread this # 2 nicely over the drive and go one or two more seasons with that. Then, after that is getting a little thin, have 4 inches of crusher run spread. If possible, have this rolled as well. If not, just rent aheavy lawn roller and roll over it a lot with your tractor and wet it a bit as you roll it. When you are done with this process, you could hot top over the crusher run, and you would have a low traffic road! Otherwise, just leave the crusher run as your final surface. Regrading with the box blade/rippers will become an annual rite of spring!
I am at the stage just before I add the crusher run, but the driveway has been holding up pretty well. I will need to get the regrading done with crusher run come spring to get the tire paths up and the streams that form in them over into the ditches.
The two best things about this approach are 1) costs are spread out over several years and 2) more tractor seat time/w3tcompact/icons/smile.gif
PaulT
The entire driveway was covered with rip-rap (also called cobbles, basically 4-5 inch stone chunks). This was left in place for the duration of the building process (about 4 months), to let the heavy equipment drive it into the ground. Then, on top of this, we spread 2-4 inches of #2 gravel. The gravel still disappears, but not at such an alarming rate. Now that I have a box blade, I can dig it up and re-spread it, too.
My recommendation is to dump the rip-rap in early spring, when its really wet, so it will sink in. This will also have the effect of leveling the low spots, more or less. I was able to drive my Saab 9000 over the big rocks, with only a little clunking, if I drove slowly and carefully. After the wet season is nearly over, have the trucks come back with #2 crushed (not washed or round, you want the little dusty stuff, too). Spread this # 2 nicely over the drive and go one or two more seasons with that. Then, after that is getting a little thin, have 4 inches of crusher run spread. If possible, have this rolled as well. If not, just rent aheavy lawn roller and roll over it a lot with your tractor and wet it a bit as you roll it. When you are done with this process, you could hot top over the crusher run, and you would have a low traffic road! Otherwise, just leave the crusher run as your final surface. Regrading with the box blade/rippers will become an annual rite of spring!
I am at the stage just before I add the crusher run, but the driveway has been holding up pretty well. I will need to get the regrading done with crusher run come spring to get the tire paths up and the streams that form in them over into the ditches.
The two best things about this approach are 1) costs are spread out over several years and 2) more tractor seat time/w3tcompact/icons/smile.gif
PaulT