Please forgive me for jumping back and forth in telling the grading job story. I know it's a little confusing as I go back and forth from the present to the past. However, it was the only way I could get you guys caught up current events. So, I'm continuing the story from where I left off
here.
After getting the grass sowed on the yard on a Monday, we focused on getting the slope of the parking pad outside the garage the way we wanted it. The week before, I had measured the grade of the parking pad using with my 10' PVC 2" pipe with a level on the pipe. The parking pad measures 30' x 40'. The 15' closest to the garage had no slope; it was level according to my crude pipe and level measurement. The 15' section farthest from the garage had all the elevation drop. What this meant was rainwater next to the house would soak through the gravel and not run away from the garage. Keep in mind, the whole reason we were re-grading the parking pad was to get it to slope away from the house. There was still a lot of dirt that needed to be scraped off the pad and hauled off!
When I talked the the contractor, he wouldn't believe my measurements. He claimed my PVC pipe would bend and that there was no way that I could measure the grade properly. So he got out his transit and started measuring. He walked around the pad quickly taking measurements by eyeballing his measuring rod while leaving the end off the ground and estimating how many inches the rod was off the ground. When I wouldn't accept his measurements and made him slow down and take accurate measurements, I eventually proved to him using his transit that my crude pipe and level measurements were correct. The 15 foot section closest to the house was level. So he got on his machine and took off more dirt. Then he had the skid steer guy clean up behind him and haul off the dirt.
I have run into the same reaction from other subs on the house building job when I measured the levelness of their work with my crude methods. For example, I had discovered that the main floor of our house was going to be 3/4" out of level by using a water level I made with a clear plastic hose and a water bucket. When I informed the original framer about the issue, he claimed that his laser level was more accurate and that my water level couldn't be trusted. It turned out that my water level measurements were right and I made the framer fix the leveling issues. The reality is, if you do things correctly and don't cause a vapor lock or undue water friction, water will always flow down hill and water bubbles will always move uphill. How do people think the NYC skyscrapers were built before lasers and electronics existed? However, it's a hopeless task to try to explain these things to some people.
So after the contractor took more dirt off the parking pad, I took more measurements with my pipe and level. I determined that at the end of our pad, we had a low spot that would not drain water. We may eventually pour concrete on the parking pad so we can't have water seeping through the gravel to a low spot under the concrete. I told the contractor on the phone about the issue and he agree he would fix that low spot before we put down gravel.
This brings us to the time of the pictures in this post. The first picture shows my wife adding some dirt near the house where the skid steer had taken off a little too much dirt near the house. Later that day we got some steady rain. Sure enough, a pond developed exactly where my "unreliable" pipe and level measurements had indicated were low areas. So for the next couple weeks, after each rain softened the top inch or so of hard red clay, I would use my box blade to remove dirt from the parking pad. I made a pile of dirt and made the contractor haul the dirt off into the woods when he came back to put down the gravel.
Even though the contractor had agreed to fix the low spot, I just didn't trust him to do it the way I wanted it so I did the work myself. Since this same scene happened time and time again while building our house, I've concluded that we are obviously way more picky that most of the contractor's customers. I don't apologize for being this way; I just recognize that's the way things are. Other people can close their eyes and just hope the builders do a good job; I couldn't do it. If I had closed my eyes, the plumbing drain pipes under our basement concrete floor would have run uphill instead of down hill. I'm not kidding; this really occurred. I could list many other such examples but won't.
The last picture shows the parking pad area just before the gravel arrived. You can see marks in the ground caused by the box blade scarifiers. We had delayed putting gravel on the parking pad about 3 weeks later than the contractor had intended. That gave me time to grade the area to the slope I wanted and gave time for the rain to pack the soil before the gravel arrived. We eventually got the pad the way we wanted it.
I'm being open about the issues we had with the grading contractor's work. What you may not be hearing much are his positive qualities. He's really not a bad guy. He has done some good things for us. He built our road/driveway and did an excellent job on it. He has been extremely busy these six months and in reality didn't have the time to devote exclusively to us. All the contractors are busy in this area because of the hail storm we got in April. I heard that 150,000 houses around here are getting new roofs. Plus there was a lot of siding and window damage. Did we get a great job done during the yard grading work? No. I would rate the quality low. In the end did we get things the way we wanted them? Yes, it just took a lot of our own time. That's not all bad. I got plenty of seat time!