Hi Bruce, I'm going to be starting a foundation soon and my property has the same fall as yours so I'm very interested in your progress.
Could you please expand on these two sentences, especially the second one. Did you hire an excavator or do the digging yourself?
Sure. I hired two excavation companies. I supervised and ran some of the equipment. Really I ran around with a builders level, grade rod and laser marking corners most of the time. We started with a goal of digging down 9' from where the uphill concrete wall sits. 9' was chosen since it would allow the entire foundation to sit on undisturbed material and I thought it would work well with the 10' concrete walls. The initial plan was to dig down to grade then dig footers.
This is what it looked like before excavation.
We started with a 90,000 pound Komatsu 300
We ran into rocks like this
When the 300 left it looked like this
The hill on the far side of the excavation and the flat area that exists beyond the current slab was built up by cutting benches in the hill below where large rocks were placed as a retaining wall and then smaller material filled in behind.
This is taken from below, and is where my gravel and pipes drain to.
Then we brought in these guys to get down to grade
Starting from far to near, the Komatsu 150 is around 40,000 pounds and outfitted with a 2' bucket to clean up rocks that are broken free. The Case is a lightweight at 20,000 pounds with I believe a 1,200 pound hammer. You can probably guess what happened when we finished drilling. The Case hammered for 5.5 days. About 60 holes were drilled. We had planned to use a 60,000 pound Komatsu 220 with an 8,000 pound hammer but we were finished before it made it out of the shop.
This guy did a lot of grading
This is what it looked like before we put gravel in. The low areas have frozen water in them. That area is primarily footer now. Additional footers were hammered out later.
Then we put gravel in
We dug / hammered out additional footers and built the center of the slab up about 8"
Water runs through the gravel, below the slab and above the solid rock below.
If I were staring over again I would excavate 8' instead of 9 so I could slope up a little leading toward the house.