bcarwell
Gold Member
I am looking at possibly purchasing a used pole barn and had a few questions. It can be found at ----->BARN FOR SALE<-------- and asking price is $5,000 (30x80 plus 10 ft overhang along the 80 and 20 ft overhang x 40 at end). Pipe and skin appears to be in fairly good shape.
Questions:
1) Sound like a reasonable price ?
2) What to watch for generally in buying pole barn being dismantled. My brother in law already warned to determine if they're just taking it down quick or to be re-assembly friendly. What should I try to get done in manner its being taken down ?
3) I'm assuming vertical poles will be cut off at slab. If they are to be embedded in new slab, the sides will have to be cut everywhere at bottom since they'll be too long. What's the work around ? Embed short poles in new slab maybe with a footing plate and having o.d. slightly smaller than i.d. of vertical poles and slide them onto the short poles and weld to plate ?
4) Best way to weld on new site with no electricity. Is amount of reassembly welding small enough that oxy-acet is feasible. Or would it make sense to buy a 5KW generator or so and a tombstone stick welder ? Or can I more feasibly fab whatever is needed (drilled plates, etc.) to connect trusses, etc. by bolting on site ?
5) Any suggestion on how to structure payment like in installments to insure the more careful disassembly initially doesn't turn into a hatchet job yet they've got all my money upfront ? They may not like committing to taking it down with only 1/3 up front.
As an aside, I plan on taking lots of pictures for reassembly. I also thought, given price of steel, I could make something smaller and sell off what's left. I put up a Metal Mart 30x30 and saw the price double inside of a year complements of the Chinese buying up steel.
Any other observations, tips ?
Thanks, Bob
Questions:
1) Sound like a reasonable price ?
2) What to watch for generally in buying pole barn being dismantled. My brother in law already warned to determine if they're just taking it down quick or to be re-assembly friendly. What should I try to get done in manner its being taken down ?
3) I'm assuming vertical poles will be cut off at slab. If they are to be embedded in new slab, the sides will have to be cut everywhere at bottom since they'll be too long. What's the work around ? Embed short poles in new slab maybe with a footing plate and having o.d. slightly smaller than i.d. of vertical poles and slide them onto the short poles and weld to plate ?
4) Best way to weld on new site with no electricity. Is amount of reassembly welding small enough that oxy-acet is feasible. Or would it make sense to buy a 5KW generator or so and a tombstone stick welder ? Or can I more feasibly fab whatever is needed (drilled plates, etc.) to connect trusses, etc. by bolting on site ?
5) Any suggestion on how to structure payment like in installments to insure the more careful disassembly initially doesn't turn into a hatchet job yet they've got all my money upfront ? They may not like committing to taking it down with only 1/3 up front.
As an aside, I plan on taking lots of pictures for reassembly. I also thought, given price of steel, I could make something smaller and sell off what's left. I put up a Metal Mart 30x30 and saw the price double inside of a year complements of the Chinese buying up steel.
Any other observations, tips ?
Thanks, Bob