jmattox1
Bronze Member
I need your help.
I have a 31'd x 37'w 2 story barn that is in bad shape (it came with the house that way purchased in Feb 02). The barn is built with 3 sides into the side of a hill and the fourth with overhead doors (10’ Great for tractor boat etc). It has a block walls first story aprox 12' tall then conventional framing second story with manufactured truss roof system. The center support 1st story is steel I-Beam. Completely open great for storage. It has Native Oak joists and sub-flooring.
Here is the problem!
The 3 block walls that sit into the hill have heaved considerable from the hydraulic pressure of the ground.
There is a natural spring that is tiled out aprox 15' out the front of the overhead door. The spring ran all summer even in the drought. I know, I tiled it last summer when I hit it by accident with the FEL. Took me 10 days to tile approximately 350’ feet to a creek.
Could I install a perimeter drain, set some dead man into the walls to reinforce them from moving, come inside saw-cut the floor (concrete), and pour a monolithic wall/s up to existing joists?
If so how large and of what material should the Dead man be?
Whew, what a mouthful!
Hope I explained well enough.
All opinions appreciated.
I have a 31'd x 37'w 2 story barn that is in bad shape (it came with the house that way purchased in Feb 02). The barn is built with 3 sides into the side of a hill and the fourth with overhead doors (10’ Great for tractor boat etc). It has a block walls first story aprox 12' tall then conventional framing second story with manufactured truss roof system. The center support 1st story is steel I-Beam. Completely open great for storage. It has Native Oak joists and sub-flooring.
Here is the problem!
The 3 block walls that sit into the hill have heaved considerable from the hydraulic pressure of the ground.
There is a natural spring that is tiled out aprox 15' out the front of the overhead door. The spring ran all summer even in the drought. I know, I tiled it last summer when I hit it by accident with the FEL. Took me 10 days to tile approximately 350’ feet to a creek.
Could I install a perimeter drain, set some dead man into the walls to reinforce them from moving, come inside saw-cut the floor (concrete), and pour a monolithic wall/s up to existing joists?
If so how large and of what material should the Dead man be?
Whew, what a mouthful!
Hope I explained well enough.
All opinions appreciated.