Indygunworks
Silver Member
I have a VERY VERY rough construction drive. I installed the drive shortly after getting my tractor and during that process is when I realized my 3pt hitch wasn't working correctly. I would have to stop and rev it WAY up to get the blade to react the way it should. I tilled about 4 inch's down and used the blade to "swipe" the dirt off. as a result I didn't get a hugely level cut.
The material I laid down for the base was recycled state spec material that was pulled up from a jobsite. Its #2 and #53 mix, w/ some dirt, and some rip rap. it was 10 bucks a ton delivered and I couldn't pass up the deal. That stuff is not easy to scoop w/ the FEL, so I assume it wont be very easy to work w/ the grader box or ripper shanks either.
Here are a few photo's of the material.




It might be hard to see, but there is definitely a high spot in the middle. its also very very wavy. average thickness is close to 4 inches, but there are a few spots closer to 6 or even 8, and several that are only 2 inch's thick.
Where the tire tracks meet the dirt to the side I could easily add at least 3 inch's of 53s (crusher run) and that will be pretty smooth and close to flush with the dirt which was the plan. I didn't expect the center to not settle like it has. Should I just leave it until construction is complete? Should I try to rip up just the middle and use the box to disperse it to the side? I sort of want to mess with the box, but it might be the first week of November before I get the parts AND have time. Maybe I should just wait until construction is complete and ask some of the heavy equip guys to drive on the higher spots to help compact it. Once I do top it and get it smooth what does the maintenance look like w/ the box?
The material I laid down for the base was recycled state spec material that was pulled up from a jobsite. Its #2 and #53 mix, w/ some dirt, and some rip rap. it was 10 bucks a ton delivered and I couldn't pass up the deal. That stuff is not easy to scoop w/ the FEL, so I assume it wont be very easy to work w/ the grader box or ripper shanks either.
Here are a few photo's of the material.




It might be hard to see, but there is definitely a high spot in the middle. its also very very wavy. average thickness is close to 4 inches, but there are a few spots closer to 6 or even 8, and several that are only 2 inch's thick.
Where the tire tracks meet the dirt to the side I could easily add at least 3 inch's of 53s (crusher run) and that will be pretty smooth and close to flush with the dirt which was the plan. I didn't expect the center to not settle like it has. Should I just leave it until construction is complete? Should I try to rip up just the middle and use the box to disperse it to the side? I sort of want to mess with the box, but it might be the first week of November before I get the parts AND have time. Maybe I should just wait until construction is complete and ask some of the heavy equip guys to drive on the higher spots to help compact it. Once I do top it and get it smooth what does the maintenance look like w/ the box?
Last edited: