I started to cut another section of our driveway last weekend. The past attachment link shows the section cut for the construction equipment, not the new section. The section shown in the attachment will have to be redone after the house construction has been completed. I plan on laying a sub base using 3" diameter rocks 3" deep, followed by 4 to 5" of 3/4" rocks. The total length of the driveway is approximately 1000' long and 16 to 20' wide. The state wants 20' width at the driveway entrance and I plan to narrow it down to 16' for the remainder. It will connect to the driveway shown in the attachment. Do you cut the crown in the earth or is the gravel contoured to a crown? I guess that both the earth and the gravel can be crowned. Also, what shape, width and depth are the drainage ditches? The driveway is not very steep and we did not notice any deep washouts before starting. Any advice would be greatly appreciated. More pictures will follow. Driveway Shot