this is in response to the 3 point concrete placer, thread,
I am getting older and my knees are not the best any more, so I started to look for a better way,
and come across the roller screed,


some of the points of the screed,


what I welded up and put in the ends of the 4" tube,



the unit is easy to use unit, (hint rub grease or duct tape on the chuck), one can stand up save the knees, and if it does not pull the mud down the first time let it roll back up over the slab and let do it again,
the company I copied uses a modified drain plug so the ends can be removed and transferred to different tube,
http://www.spinscreed.com/ videos and other at the site,
they used an aluminum tube and I used a steel tube, lower cost for me,
I am getting older and my knees are not the best any more, so I started to look for a better way,
and come across the roller screed,


some of the points of the screed,


what I welded up and put in the ends of the 4" tube,



the unit is easy to use unit, (hint rub grease or duct tape on the chuck), one can stand up save the knees, and if it does not pull the mud down the first time let it roll back up over the slab and let do it again,
the company I copied uses a modified drain plug so the ends can be removed and transferred to different tube,
http://www.spinscreed.com/ videos and other at the site,
they used an aluminum tube and I used a steel tube, lower cost for me,