gable74
Member
- Joined
- Jun 28, 2021
- Messages
- 45
- Location
- East Coast - Maryland
- Tractor
- Bobcat 553, Deere 757, Deere 737, Deere G100
Spent the better part of a year reading various posts on the net and looking at some actual bridges at parks here in the area before I got going. Quite a bit of good info came from this site so I figured I would post up my progress. Here is a short explanation of of what I have so far with some pics.
Bridge was required because our 36 acres was divided by this creek and we wanted easy accessibility to the other side.
Bridge needed to support people/ATVs only. No vehicles.
Bottom of poles will be about 42" above average water surface. Been here for 30 years and water has never risen more than a foot even during flood stage.
Went with (6) 14" x 30' utility poles.
Bridge deck will be 84" wide with the outer poles 50" apart. Third pole centered between the two.
Ripped a flat edge on one side of the poles for the deck boards as the poles were a little bumpy.
Hand dug (6) 16" x 48" footers that are spanned with doubled up 6" x 6" x 8' supports.
Three supports roughly 24' apart.
Had a local lumber mill cut 2" x 8" x 84" white oak planks for the deck. Not nominal, but real 2" thick boards.
Plan on using some unistrut at the mid point (12') of both spans to "tie" all three poles together. Essentially like a clamp.
The bridge is down a long winding trail that is 48" wide at most and the better part of 1/4 mile from the garage, making getting material there a real challenge. The utility poles weighed at least 1200lbs because the E20 excavator was screaming to lift them. Not to mention humping the 80lb bags of sackrete back there, only about 70 bags though...
.
Due to terrain the poles had to be dragged the last 50 yards down the hill and manually placed on the supports. This was quite the task but we did not want to sacrifice the characteristics of the trail by opening it up wide enough for the excavator, not to mention the logistics of trying to navigate a 1200lb, 30' pole through winding trails. Trees kept getting in the way
.
My wife is a park ranger here in the area so I was lucky enough to be able to consult some trail folks who work for the park system before getting under way. I got their stamp of approval.
I plan on getting the deck boards started this weekend, or whenever the outside temps drop to a level I can work outside without having a heart attack.
Anyway, here is what we have so far:
Bridge was required because our 36 acres was divided by this creek and we wanted easy accessibility to the other side.
Bridge needed to support people/ATVs only. No vehicles.
Bottom of poles will be about 42" above average water surface. Been here for 30 years and water has never risen more than a foot even during flood stage.
Went with (6) 14" x 30' utility poles.
Bridge deck will be 84" wide with the outer poles 50" apart. Third pole centered between the two.
Ripped a flat edge on one side of the poles for the deck boards as the poles were a little bumpy.
Hand dug (6) 16" x 48" footers that are spanned with doubled up 6" x 6" x 8' supports.
Three supports roughly 24' apart.
Had a local lumber mill cut 2" x 8" x 84" white oak planks for the deck. Not nominal, but real 2" thick boards.
Plan on using some unistrut at the mid point (12') of both spans to "tie" all three poles together. Essentially like a clamp.
The bridge is down a long winding trail that is 48" wide at most and the better part of 1/4 mile from the garage, making getting material there a real challenge. The utility poles weighed at least 1200lbs because the E20 excavator was screaming to lift them. Not to mention humping the 80lb bags of sackrete back there, only about 70 bags though...
Due to terrain the poles had to be dragged the last 50 yards down the hill and manually placed on the supports. This was quite the task but we did not want to sacrifice the characteristics of the trail by opening it up wide enough for the excavator, not to mention the logistics of trying to navigate a 1200lb, 30' pole through winding trails. Trees kept getting in the way
My wife is a park ranger here in the area so I was lucky enough to be able to consult some trail folks who work for the park system before getting under way. I got their stamp of approval.
I plan on getting the deck boards started this weekend, or whenever the outside temps drop to a level I can work outside without having a heart attack.
Anyway, here is what we have so far:
Attachments
-
20210320_145644.jpg3.9 MB · Views: 1,230
-
20210404_151353.jpg3.4 MB · Views: 1,240
-
20210418_115559.jpg2.4 MB · Views: 1,043
-
20210420_172736.jpg2.5 MB · Views: 966
-
20210530_154713.jpg3.6 MB · Views: 965
-
20210530_155321.jpg4 MB · Views: 1,063
-
20210531_123944.jpg4.2 MB · Views: 981
-
20210619_073840.jpg3.1 MB · Views: 956
-
20210619_074439.jpg2.9 MB · Views: 968
-
20210619_075818.jpg2.4 MB · Views: 1,240
Last edited: