Building 55' Bridge Across Creek - Utility Poles

   / Building 55' Bridge Across Creek - Utility Poles #1  

gable74

Member
Joined
Jun 28, 2021
Messages
45
Location
East Coast - Maryland
Tractor
Bobcat 553, Deere 757, Deere 737, Deere G100
Spent the better part of a year reading various posts on the net and looking at some actual bridges at parks here in the area before I got going. Quite a bit of good info came from this site so I figured I would post up my progress. Here is a short explanation of of what I have so far with some pics.

Bridge was required because our 36 acres was divided by this creek and we wanted easy accessibility to the other side.
Bridge needed to support people/ATVs only. No vehicles.
Bottom of poles will be about 42" above average water surface. Been here for 30 years and water has never risen more than a foot even during flood stage.
Went with (6) 14" x 30' utility poles.
Bridge deck will be 84" wide with the outer poles 50" apart. Third pole centered between the two.
Ripped a flat edge on one side of the poles for the deck boards as the poles were a little bumpy.
Hand dug (6) 16" x 48" footers that are spanned with doubled up 6" x 6" x 8' supports.
Three supports roughly 24' apart.
Had a local lumber mill cut 2" x 8" x 84" white oak planks for the deck. Not nominal, but real 2" thick boards.
Plan on using some unistrut at the mid point (12') of both spans to "tie" all three poles together. Essentially like a clamp.

The bridge is down a long winding trail that is 48" wide at most and the better part of 1/4 mile from the garage, making getting material there a real challenge. The utility poles weighed at least 1200lbs because the E20 excavator was screaming to lift them. Not to mention humping the 80lb bags of sackrete back there, only about 70 bags though...:rolleyes:.

Due to terrain the poles had to be dragged the last 50 yards down the hill and manually placed on the supports. This was quite the task but we did not want to sacrifice the characteristics of the trail by opening it up wide enough for the excavator, not to mention the logistics of trying to navigate a 1200lb, 30' pole through winding trails. Trees kept getting in the way :).

My wife is a park ranger here in the area so I was lucky enough to be able to consult some trail folks who work for the park system before getting under way. I got their stamp of approval.

I plan on getting the deck boards started this weekend, or whenever the outside temps drop to a level I can work outside without having a heart attack.

Anyway, here is what we have so far:
 

Attachments

  • 20210320_145644.jpg
    20210320_145644.jpg
    3.9 MB · Views: 1,230
  • 20210404_151353.jpg
    20210404_151353.jpg
    3.4 MB · Views: 1,240
  • 20210418_115559.jpg
    20210418_115559.jpg
    2.4 MB · Views: 1,043
  • 20210420_172736.jpg
    20210420_172736.jpg
    2.5 MB · Views: 966
  • 20210530_154713.jpg
    20210530_154713.jpg
    3.6 MB · Views: 965
  • 20210530_155321.jpg
    20210530_155321.jpg
    4 MB · Views: 1,063
  • 20210531_123944.jpg
    20210531_123944.jpg
    4.2 MB · Views: 981
  • 20210619_073840.jpg
    20210619_073840.jpg
    3.1 MB · Views: 956
  • 20210619_074439.jpg
    20210619_074439.jpg
    2.9 MB · Views: 968
  • 20210619_075818.jpg
    20210619_075818.jpg
    2.4 MB · Views: 1,240
Last edited:
   / Building 55' Bridge Across Creek - Utility Poles
  • Thread Starter
#2  
Here are the poles in place and a deck board or two after I spent a while getting everything level/plumb. I will be cutting off the cantilevered ends of the poles on the far side where I will start my ramp. The other end will dead end into the earth for a smooth transition.
 

Attachments

  • 20210619_094203.jpg
    20210619_094203.jpg
    4 MB · Views: 784
  • 20210622_185401.jpg
    20210622_185401.jpg
    2.7 MB · Views: 723
  • 20210627_153550.jpg
    20210627_153550.jpg
    3.4 MB · Views: 714
   / Building 55' Bridge Across Creek - Utility Poles #4  
Nice to see the use of all that manual labor in order to maintain the present aesthetic environment. Good work !!

gg
 
   / Building 55' Bridge Across Creek - Utility Poles #6  
Bad a$$. Well engineered, sir.

One immediate question: That creek looks pretty small. Did you consider a trail re-alignment that might have allowed you to have a much, much shorter overall bridge length? Looks like you go over a pond for the first half that you could have possible just gone around.

I wanted rough sawn white oak for my own bridge decking also, but local sawyers kept ignoring my inquiries, and then I came into some free decking anyway. What did those 84" boards run ya?
 
   / Building 55' Bridge Across Creek - Utility Poles #7  
Very nice work! Years ago when building my shorter (10') bridge I couldn't find poles to save my life.
 
   / Building 55' Bridge Across Creek - Utility Poles
  • Thread Starter
#8  
I appreciate the kind words all, thank you.
 
   / Building 55' Bridge Across Creek - Utility Poles
  • Thread Starter
#9  
One immediate question: That creek looks pretty small. Did you consider a trail re-alignment that might have allowed you to have a much, much shorter overall bridge length? Looks like you go over a pond for the first half that you could have possible just gone around.

I wanted rough sawn white oak for my own bridge decking also, but local sawyers kept ignoring my inquiries, and then I came into some free decking anyway. What did those 84" boards run ya?

When the creek "floods" it widens but doesn't really rise, so I had to be particular about where and how I crossed the area. The first span crosses more of a vernal pool during dry weather and changes to a pond during the wet season. If you looked at the area on a Topo you would get a better understanding, but the elevation on either side of the creek rises about 50' in a very short span. It is the equivalent of about a 10/12 roof pitch. I still came in and "cleaned up" the existing trail to the creek creating a bench cut to level things out, but I really did not want to open things up any more than that. As long as I can get my cart through comfortably, that is all we wanted.

We live on the east coast and within a couple hours of the shore, such we have plenty of vendors who cater to boats, piers, etc., which made finding utility poles and pilings simple enough. I purchased (6) brand new poles for a little over $1500. I had options for used poles, but not knowing what stresses they had been through already, I bit the bullet on new ones.

The white oak planks look fantastic and luckily we have plenty of small mills in the area who love this kind of work. I paid a little over $12 per board and I will need about 105 boards to complete the deck and ramp. If I had to change one thing, it would be the width of the boards from 8" to maybe 10" or 12". It would have cut down the amount of boards, but would have been tougher to get back there because of the weight. Hoping they do not shrink up too much.

The hardest part was getting the poles that last 50 yards down the hill, taking 8 guys to just drag them, luckily since we had to go down the hill, gravity was on our side.
The second hardest part was ripping a straight edge along the grain of (6) dense poles....lol.

Tough to tell from the pics, but having this large bridge nestled in the middle of the woods with only small trails to and from, gives it a very cool feel.

If anyone has any suggestions or questions, just let me know!

I will post up more pics as the project continues.
 

Attachments

  • 20210617_084249.jpg
    20210617_084249.jpg
    2.9 MB · Views: 326
Last edited:
   / Building 55' Bridge Across Creek - Utility Poles #10  
Keep the pictures coming, this is an interesting project to follow!
 

Tractor & Equipment Auctions

2016 Chevrolet Impala Limited Sedan (A48082)
2016 Chevrolet...
2001 Nissan Frontier Crew Cab Pickup Truck (A48081)
2001 Nissan...
PTO Pump (A50860)
PTO Pump (A50860)
2014 Ford F-350 Altec AT200A Insulated Crane Service Truck (A48081)
2014 Ford F-350...
2017 Chevrolet Silverado 1500 Crew Cab Pickup Truck (A48081)
2017 Chevrolet...
2025 Swict 72in Bucket Skid Steer Attachment (A49346)
2025 Swict 72in...
 
Top